Fatface and Capital had a long-term partnership going back many years. Fat Face approached Capital about their new distribution centre in Hampshire and how best to make the site efficient with the baling of cardboard which was going to be produced on three mezzanine floors and a ground floor warehouse.
Once Built, Its Time for Delivery and Installation
Ground Floor Chute Assembly
Capital designed a chute solution which enabled facts access for used cardboard boxes. To complement this application, Capital Compactors also proposed a semi-automatic baler which would start and stop automatically when the machine was full of cardboard.
Its been Planned Well - All completed in One Day.
Ground Floor Loading
On the 8th of May, our in-house engineering team delivered and installed the equipment. The next day, the team trained the Fat Face staff and handed the system over for many years of reliable cardboard baling.
Full On-Site Certificated Training Completed
Baler designed and built was the CHB45 semi-automatic baler.
First 500kg Baler Made
Proud Invite to the Official Open Day